Production results 2014 |
|||
---|---|---|---|
| Planed production |
Realized production |
Index |
| GWh |
GWh |
Realized / Planned |
TEC |
4.577,9 |
3.506,4 |
76,6% |
|
|
|
|
Bitola 1 |
1.224,4 |
851,1 |
69,5% |
Bitola 2 |
1.496,6 |
1.207,6 |
80,7% |
Bitola 3 |
1.507,7 |
1.258,2 |
83,5% |
Oslomej |
349,4 |
189,6 |
54,3% |
|
|
|
|
HEC |
1.159,8 |
958,2 |
82,6% |
|
|
|
|
Vrutok |
297,5 |
325,8 |
109,5% |
Raven |
35,7 |
37,9 |
106,1% |
Vrben |
36,9 |
34,4 |
93,2% |
Shpilje |
282,6 |
190,3 |
67,3% |
Globocica |
181,2 |
136,2 |
75,2% |
Tikvesh |
132,2 |
116,1 |
87,8% |
Kozjak |
134,4 |
80,4 |
59,8% |
Sveta Petka |
59,2 |
37,2 |
62,8% |
|
|
|
|
TE-TP Energetika |
19,6 |
0,0 |
0,0% |
VEC Bogdanci |
39,7 |
70,4 |
177,1% |
TOTAL |
5.797,0 |
4.535,0 |
78,2% |
Compared to the planned production for 2014, JSC ELEM has achieved production of 4.535,0 GWh, which is 78.2% achievement of the planned production. In that thermal power plants have achieved 76.6% of planned production, hydropower plants have produced 82.6% of the planned and the wind power plants have achieved 77.1% more than planned production.